Sponsored Links

Selasa, 24 April 2018

Sponsored Links

Abstract Word Cloud For Overall Equipment Effectiveness With ...
src: previews.123rf.com

Overall equipment effectiveness (OEE) is a term coined by Seiichi Nakajima in the 1960s to evaluate how effectively a manufacturing operation is utilized. It is based on the Harrington Emerson way of thinking regarding labor efficiency. The results are stated in a generic form which allows comparison between manufacturing units in differing industries. It is not however an absolute measure and is best used to identify scope for process performance improvement, and how to get the improvement. If for example the cycle time is reduced, the OEE will increase i.e. more product is produced for less resource. Another example is if one enterprise serves a high volume, low variety market, and another enterprise serves a low volume, high variety market. More changeovers (set-ups) will lower the OEE in comparison, but if the product is sold at a premium, there could be more margin with a lower OEE.

OEE measurement is also commonly used as a key performance indicator (KPI) in conjunction with lean manufacturing efforts to provide an indicator of success. OEE can be illustrated by a brief discussion of the six metrics that comprise the system. The hierarchy consists of two top-level measures and four underlying measures.


Video Overall equipment effectiveness



Top-level metrics

Overall equipment effectiveness (OEE) and total effective equipment performance (TEEP) are two closely related metrics that report the overall utilization of facilities, time and material for manufacturing operations. These top view metrics directly indicate the gap between actual and ideal performance.

  • Overall equipment effectiveness (OEE) quantifies how well a manufacturing unit performs relative to its designed capacity, during the periods when it is scheduled to run.
  • Total effective equipment performance (TEEP) measures OEE against calendar hours, i.e.: 24 hours per day, 365 days per year.

Maps Overall equipment effectiveness



Underlying metrics

In addition to the above measures, there are four underlying metrics that provide understanding as to why and where the OEE and TEEP gaps exist.

The measurements are described below

  • Loading: The portion of the TEEP Metric that represents the percentage of total calendar time that is actually scheduled for operation.
  • Availability: The portion of the OEE Metric that represents the percentage of scheduled time that the operation is available to operate. Often referred to as Uptime.
  • Performance: The portion of the OEE Metric that represents the speed at which the Work Center runs as a percentage of its designed speed.
  • Quality: The portion of the OEE Metric that represents the Good Units produced as a percentage of the Total Units Started. It is commonly referred to as the first pass yield (FPY).

Overall Equipment Effectiveness - Lean Strategies International
src: www.leanstrategiesinternational.com


Calculations for OEE and TEEP

What follows is a detailed presentation of each of the six OEE / TEEP Metrics and examples of how to perform calculations. The calculations are not particularly complicated, but care must be taken as to standards that are used as the basis. Additionally, these calculations are valid at the work center or part number level but become more complicated if rolling up to aggregate levels.

Overall equipment effectiveness

OEE breaks the performance of a manufacturing unit into three separate but measurable components: Availability, Performance, and Quality. Each component points to an aspect of the process that can be targeted for improvement. OEE may be applied to any individual Work Center, or rolled up to Department or Plant levels. This tool also allows for drilling down for very specific analysis, such as a particular Part Number, Shift, or any of several other parameters. It is unlikely that any manufacturing process can run at 100% OEE. Many manufacturers benchmark their industry to set a challenging target; 85% is not uncommon.

  • OEE is calculated with the formula (Availability)*(Performance)*(Quality)
  • Using the examples given below:
  • (Availability= 86.6%)*(Performance=93%)*(Quality=91.3%)= (OEE=73.6%)

Alternatively, and often easier, OEE is calculated by dividing the minimum time needed to produce the parts under optimal conditions by the actual time needed to produce the parts. For example:

  • Total Time: 8 hour shift or 28,800 seconds, producing 14,400 parts, or one part every 2 seconds.
  • Fastest possible cycle time is 1.5 seconds, hence only 21,600 seconds would have been needed to produce the 14,400 parts. The remaining 7,200 seconds or 2 hours were lost.
  • The OEE is now the 21,600 seconds divided by 28,800 seconds (same as minimal 1.5 seconds per part divided by 2 actual seconds per part), or 75%.

Total effective equipment performance

Where OEE measures effectiveness based on scheduled hours, TEEP measures effectiveness against calendar hours, i.e.: 24 hours per day, 365 days per year.

TEEP, therefore, reports the 'bottom line' utilization of assets.

TEEP = Loading * OEE

Loading

The Loading portion of the TEEP Metric represents the percentage of time that an operation is scheduled to operate compared to the total Calendar Time that is available. The Loading Metric is a pure measurement of Schedule Effectiveness and is designed to exclude the effects how well that operation may perform.

Calculation: Loading = Scheduled Time / Calendar Time

Example:

A given Work Center is scheduled to run 5 Days per Week, 24 Hours per Day.

For a given week, the Total Calendar Time is 7 Days at 24 Hours.

Loading = (5 days x 24 hours) / (7 days x 24 hours) = 71.4%

Availability

The Availability portion of the OEE Metric represents the percentage of scheduled time that the operation is available to operate. The Availability Metric is a pure measurement of Uptime that is designed to exclude the effects of Quality, Performance, and Scheduled Downtime Events. The losses due to wasted availability are called availability losses.

Example: A given Work Center is scheduled to run for an 8-hour (480 minute) shift with a 30-minute scheduled break and experiences 60 minutes of unplanned (breakdown) time. In this case, the 30 minute break should be considered "scheduled time" although it is planned downtime.

Operating Time = 480 Minutes Scheduled - 30 Minutes Scheduled Downtime - 60 Minutes Unscheduled Downtime = 390 Minutes

Calculation: Availability = operating time / scheduled time

Availability = 390 minutes / 480 minutes = 81.25%

Performance and productivity

Also known as "process rate", the Performance portion of the OEE Metric represents the speed at which the Work Center runs as a percentage of its designed speed. The Performance Metric is a pure measurement of speed that is designed to exclude the effects of Quality and Availability. The losses due to wasted performance are also often called speed losses. In practice it is often difficult to determine speed losses, and a common approach is to merely assign the remaining unknown losses as speed losses.

Calculation: Performance (Productivity) = (Parts Produced * Ideal Cycle Time) / Operating time

Example:

A given Work Center is scheduled to run for an 8-hour (480 minute) shift with a 30-minute scheduled break.

Operating Time = 450 Min Scheduled - 60 Min Unscheduled Downtime = 390 Minutes

The Standard Rate for the part being produced is 40 Units/Hour or 1.5 Minutes/Unit

The Work Center produces 242 Total Units during the shift. Note: The basis is Total Units, not Good Units. The Performance metric does not penalize for Quality.

Time to Produce Parts = 242 Units * 1.5 Minutes/Unit = 363 Minutes

Performance (Productivity) = 363 Minutes / 390 Minutes = 93.0%

Quality

The Quality portion of the OEE Metric represents the Good Units produced as a percentage of the Total Units Started. The Quality Metric is a pure measurement of Process Yield that is designed to exclude the effects of Availability and Performance. The losses due to defects and rework are called quality losses.

Calculation: Quality = (Units produced - defective units) / (Units produced)

Example:

242 Units are produced. 21 are defective.

(242 units produced - 21 defective units) = 221 units

221 good units / 242 total units produced = 91.32%


SAP Overall Equipment Effectiveness (OEE) - YouTube
src: i.ytimg.com


"Six Big Losses"

To be able to better determine what is contributing to the greatest loss and so what areas should be targeted to improve the performance, these categories (Availability, Performance and Quality) have been subdivided further into what is known as the 'Six Big Losses' to OEE.

These are categorized as follows:

The reason for identifying the losses in these categories is so that specific countermeasures can be applied to reduce the loss and improve the overall OEE.


OEE[OVERALL EQUIPMENT EFFECTIVENESS] ADVANCE COURSE PART 1 - YouTube
src: i.ytimg.com


Heuristic

OEE is useful as a heuristic, but can break down in several circumstances. For example, it may be far more costly to run a facility at certain times. Performance and quality may not be independent of each other or of availability and loading. Experience may develop over time. Since the performance of shop floor managers is at least sometimes compared to the OEE, these numbers are often not reliable, and there are numerous ways to fudge these numbers.

OEE has properties of a geometric mean. As such it punishes variability among its subcomponents. For example, 20% * 80% = 16%, whereas 50% * 50% = 25%. When there are asymmetric costs associated with one or more of the components, then the model may become less appropriate.

Consider a system where the cost of error is exceptionally high. In such a condition, higher quality may be far more important in a proper evaluation of effectiveness than performance or availability. OEE also to some extent assumes a closed system and a potentially static one. If one can bring in additional resources (or lease out unused resources to other projects or business units) then it may be more appropriate for example to use an expected net present value analysis.

Variability in flow can also introduce important costs and risks that may merit further modeling. Sensitivity analysis and measures of change may be helpful.


What is Overall Equipment Effectiveness (OEE)? - YouTube
src: i.ytimg.com


Further reading

  • Hansen, Robert C (2005). Overall Equipment Effectiveness (OEE). Industrial Press. ISBN 978-0-8311-3237-8. 
  • Koch, Arno (2007). OEE for the Production Team. Makigami. ISBN 978-90-78210-08-5. (English). ISBN 978-90-78210-07-8 (Dutch)., ISBN 978-3-940775-04-7 (German). 
  • Productivity Press Development Team (1999), OEE for Operators: Overall Equipment Effectiveness, Productivity Press, ISBN 978-1-56327-221-9 

Getting to OEE... - Hertzler Systems Inc
src: www.hertzler.com


See also

  • Total productive maintenance

Overall Equipment Effectiveness (OEE) Calculation - YouTube
src: i.ytimg.com


References

Source of the article : Wikipedia

Comments
0 Comments